Usiminas Puts Replacement BOF on Order
05/18/2021 - Brazil’s Usinas Siderúrgicas de Minas Gerais S.A. (Usiminas) has contracted Danieli Corus to build a replacement converter for its Ipatinga integrated steelworks.
According to the equipment manufacturer, the 180-metric-ton converter will be equipped with a Danieli-patented suspension system based on a vertical Lamella arrangement, an air-cooling system for the vessel barrel, and water–based cooling for the vessel’s top cone.
The new converter will replace the No. 5 unit at the No. 2 BOF shop. The first heat is scheduled to take place in 2023.
Separately, Usiminas on Thursday announced it would postpone a planned rebuild of the Ipatinga mill's No. 3 blast furnace, citing the on-going effects of the COVID-19 pandemic and the unit's stable performance.
Usiminas said that with the 10-month postponement, the furnace will now remain in operation until mid-2023.



.jpg?lang=en-US&ext=.jpg)
.gif?width=220&height=200&mediaprotectionhash=374c6b9a31f2b2fbfc7937391034efb46fd57feba997b9ad2ae9a0bd3d48329d&ext=.gif)

.gif?width=100&height=200&mediaprotectionhash=e2d5b15d68f84f22038524be6c58e5268d67b7f44494b544e29a8d53c5b959ba&ext=.gif)