NLMK Kaluga Commissions Energy Infrastructure Facilities
04/10/2013 - Earlier this year, NLMK Kaluga completed the construction and commissioning of the first stage of its step-down steelmaking plant substation and a 220 kW 47.6 km long transmission line.
Earlier this year, NLMK Kaluga completed the construction and commissioning of the first stage of its step-down steelmaking plant substation and a 220 kW 47.6 km long transmission line.
Distribution substations were put on stream to supply main and auxiliary steelmaking equipment.
Power cables were installed to connect substations directly to production facilities.
NLMK Kaluga, part of the NLMK Group, is a mini mill being built in the Kaluzhskaya region of Russia. Siemens is supplying the melting equipment and SMS Meer is providing the rolling shop equipment. Start-up of the first phase is scheduled for the first part of 2013.