08/19/2014 - In June 2014, Russian special steel producer Ruspolymet assigned INTECO with the engineering and supply of a 6t vacuum arc remelting (VAR) plant.
This was the second follow-up order for INTECO: This new VAR furnace follows the 10t ESR plant sold in fall 2013 and the 2012 VIM project. The VIM is being assembled and the ESR furnace is about to be delivered. Obviously there is no better evidence of the customer’s satisfaction with INTECO’s work than placing this new order.
The produced ingots will have a maximum diameter of 700 mm and an approximate weight of 6t. Furthermore the newly developed INTECO Level 2 system will allow Ruspolymet to administrate, metallurgically guide and optimize the whole process chain — VIM, ESR, and VAR.
Right now Ruspolymet and INTECO are discussing further joint projects and a possible future strategic partnership.
The produced ingots will have a maximum diameter of 700 mm and an approximate weight of 6t. Furthermore the newly developed INTECO Level 2 system will allow Ruspolymet to administrate, metallurgically guide and optimize the whole process chain — VIM, ESR, and VAR.
Right now Ruspolymet and INTECO are discussing further joint projects and a possible future strategic partnership.