Open / Close Advertisement

Egyptian Mill’s Furnace Upgrade Yields Big Fuel Savings 

According to Danieli, the project entailed installation of a new combustion system, a new recuperator and a new automation system. The goal of the project was to reduce fuel consumption by 25%. Not only was the goal met, but exceeded by an additional 20% reduction, Danieli said. 

“The outstanding performance led to an extremely quick final acceptance for the project,” Danieli said in a statement.